试卷: LEED v4 OM模拟题D卷英文[查看]   A project with an evaporative condenser uses 100% potable water for cooling. Which action would the project owner need to take to achieve WE Credit Cooling Tower Water Use?
 项目有蒸发式制冷系统,完全使用自来水,那怎么样可以满足WE得分点冷却塔用水的要求
    A: Submeter the non-potable water use 对非自来水水源进行分项计量 B: Hire a water treatment professional to conduct a potable water analysis 让水处理机构检测自来水水质 C: Offset the potable water use with at least 10% non-potable water 降低10%的自来水消耗,用回收水源替代 D: Share any metering data with USGBC for five years 将用水数据与USGBC共享5年     参考答案: B 
  本题解释: 选择B,本题解释The first step for this credit is a potable water analysis to identify the concentration parameters in the condenser water. |   
 
  
 |