试卷: LEED v4 OM模拟题D卷英文[查看] A project team has a facility maintenance and renovation policy for a hospital. During the performance period several operating rooms will be renovated. What does the project team need to do prior to renovation activities begin?
项目团队为一个医院项目制定了设施维护与翻新政策,在绩效期内有几个房间进行了翻新,项目团队需要在翻新工作开始前做什么工作
A: Update the CFR 更新现有设施要求 B: Adapt the plan to fit the scheduled activities 根据翻新工作的进度来调整政策内容 C: Conduct air quality testing to set a baseline for IAQ 在翻新工作开始之前进行室内空气品质测试 D: Purchase carbon offsets to mitigate construction emissions 购买碳补偿来抵消施工的排放 参考答案: B
本题解释: 选择B,本题解释The plan for the prerequisite serves as a guideline. For each renovation project the plan has to be updated to reflect the scope of work. The waste management plan for each renovation during the performance period must be submitted for credit documentation. |
|