Members of a project team are discussing blending potable and reclaimed water for use in a cooling tower. Which issue should be addressed when considering this strategy?
项目团队成员正在讨论混合饮用水和回收水,将其用于冷却塔。当采用这项策略时,应考虑应对以下哪项问题?

A: Both types of water should be tested first. 首先两种类型的水都应该被测试下
B: The building maintenance staff will first need additional training. 建筑运营团队将最先需要额外培训
C: Blending is not acceptable for LEED credit. 混合水不被LEED 得分接受
D: The life cycle of the cooling tower will be extended as a result. 冷却塔的生命周期将被延长

参考答案: A

本题解释:
选择A,本题解释The different water types should be tested to see what dissolved solids exist.
Potable water with high phosphates and a reclaimed water supply with high calcium may form calcium phosphate, which will lead to scaling in the condenser.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-9-12 09:10 , Processed in 0.077145 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部