试卷: LEED v4 OM模拟题B卷英文[查看]   A campus project has extensive landscaping and organic waste. What can be used as a strategy to divert plant material from landfills that would qualify for SS Credit Site Management?
 某学校项目有很多景观和有机废弃物。可以采取哪项措施将种植材料从垃圾填埋场中转移,以符合SS得分项 场地管理的要求?   A: Using backpack blowers to blow the waste onto streets outside the property lines.使用鼓风机将废弃物吹到项目边界之外 B: Diverting to a waste-to-energy facility 将其转移到 废弃物能源转换 设施中 C: Diverting no more than 50% of the materials to landfills 将不超过50%的材料进行填埋 D: Spraying the waste with herbicides 用除草剂喷洒废弃物     参考答案: B 
  本题解释: 选择B,本题解释Waste-to-energy is an acceptable solution for the credit. |   
 
  
 |