A project team is reviewing a project\\\'s goals. What type of analysis would be

[复制链接]

1759

主题

1

好友

5712

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2016-12-22 11:37:53 |只看该作者 |倒序浏览
试卷: LEED v4 OM模拟题A卷英文[查看]
A project team is reviewing a project\'s goals. What type of analysis would be appropriate for existing building commissioning?
项目团队正在审查项目目标。什么类型的分析适合既有建筑调试?
A: Documentation is outdated 过时的文档
B: The focus is on proper system operations重点是正确的系统操作
C: The building is older and hasn\'t been retrofitted recently 该建筑物较旧,最近没有改造过
D: The owner wants to make major upgrades to the building envelope 业主准备对建筑电梯进行更新

参考答案: B

本题解释:
选择B,本题解释 The Existing Building Commissioning option focuses more on controls, proper system operations and efficiency improvements.
The other choices would benefit from an ASHRAE Level 2 Energy Survey and Analysis.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-9-12 10:26 , Processed in 0.075067 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部