试卷: LEED v4 ID+C模拟题C卷英文[查看] A project team member is reviewing the project design to verify if the appropriate tenant-level and system-level advanced energy meters are installed. The building is cooled by electricity and heated by natural gas. Which statement must be true for the project to achieve EA Credit Advanced Energy Metering? A: Temporary meters must be used in case the meters need to be moved as tenant spaces increase. B: Either the electricity or gas can be metered. C: The system must be capable of storing data for at least five years. D: Each meter must record data at least hourly. 参考答案: D
本题解释: Notes:A:Meters must be permanently installed.B:Any energy use must be metered that is used in the tenant space.C:Data must be stored for thirty-six months, not five years.D:Meters must be permanently installed, record at intervals of one hour or less, and transmit data to a remote location. |
|