A building contractor with limited space on the project site has one constructio

[复制链接]

1759

主题

1

好友

5712

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2016-9-30 15:35:01 |只看该作者 |倒序浏览
试卷: LEED v4 ID+C模拟题C卷英文[查看]
A building contractor with limited space on the project site has one construction and waste-management bin that commingles concrete, wood, and drywall, as well as a separate bin for land-clearing debris. A waste hauler takes the dumpsters and separates the concrete, wood, and drywall off site for recycling. Given this information, which statement is true?
A: The concrete, wood, and drywall are counted as three waste streams, and the land clearing debris is counted as one waste stre
B: The concrete, wood, and drywall are considered one waste stream, and the land-clearing debris is not counted as one waste str
C: The materials are counted as two waste streams.
D: None of the materials are counted as a waste stream.

参考答案: B

本题解释:
Notes:B:ADC and land-clearing debris are not counted as waste streams.
For LEED, a waste stream should constitute at least 5% by weight or volume of the project\'s totaled diverted waste. The waste stream can be a material category that is diverted or a mixture of several material categories that are diverted.
The commingled materials count as one stream even though the hauler separates them out later off site.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-9-12 23:12 , Processed in 0.079216 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部