An office project will include 30% incomplete space when the project team submits the final application for LEED certification. The space will be completed by the tenant. What supplemental documentation must be provided?

A: Signed credit forms by the tenant
B: Current facilities requirements with additional space to document the future changes
C: Letter of commitment from the tenant
D: A set of nonbinding tenant design and construction guidelines that include an explanation of the project circumstances No mor

参考答案: D

本题解释:
选择D,本题解释When the tenant is finishing the incomplete space include a set of nonbinding tenant design and construction guidelines that include an explanation of the project circumstances.

Otherwise the building owner must submit:

\'Submit a letter of commitment, signed by the owner, indicating that the remaining incomplete spaces will satisfy the requirements of each prerequisite and credit achieved by this project if and when completed by the owner.\' - USGBC
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-9-12 18:55 , Processed in 0.078439 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部