试卷: WELL AP模拟题英文B卷[查看] The project manager of a museum renovation is scheduling abatement activities for asbestos and lead. What other hazardous material should the project manager abate if present in the building? 博物馆装修的项目经理正在安排石棉和铅的清除活动。项目经理还应清除哪些其他有害物质,如果他们出现在建筑物内? A: PCB 多氯联苯 B: Mercury 汞 C: Urea formaldehyde 脲醛树脂 D: PVC 聚氯乙烯 参考答案: A
本题解释: 正确答案:A
解析:A:This is the correct answer. Project teams must conduct evaluation and abatement of PCBs.
B:Feature 11 Fundamental Material Safety requires evaluation and abatement for asbestos, lead, and Polychlorinated Biphenyl (PCB).
C:Urea formaldehyde is not addressed in Feature 11.
D:PVC is not addressed in Feature 11. |
|