试卷: LEED v4 BD+C英文模拟题(A)[查看] Why should a project team for a new office project conduct a site inventory and corresponding site analysis for project site? A: To ensure certification B: To streamline any Sustainable Sites credits pursued C: To identify synergies between the assessment and other LEED credits D: To meet the SS Credit Rainwater Management site inventory requirement 参考答案: C
本题解释: 正确答案:C
解析:C:Because the assessment is completed early in the project,it allows the project team to identify synergies with other LEED credits.
A:Site Assessment is not a prerequisite and thus not required for certification.
B:This is not true.