A project team is planning to restore the soil and habitat of a previously devel

[复制链接]

1759

主题

1

好友

5712

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2015-4-13 09:15:01 |只看该作者 |倒序浏览
试卷: LEED v4 BD+C英文模拟题(A)[查看]
A project team is planning to restore the soil and habitat of a previously developed site in parallel. When identifying the areas to be restored,which elements can the project team exclude from the calculations?
A: Compacted dirt roads
B: Areas used for heavily wheeled traffic
C: Vegetated landscape areas that are constructed to accommodate rainwater infiltration
D: Equipment storage areas

参考答案: C

本题解释:
正确答案:C
解析:C:This type of area can be excluded.
The remaining choices are all types of areas that would have compacted areas that need to be restored.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-9-14 01:59 , Processed in 0.074276 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部