试卷: LEED v4 GA模拟题A卷中文[查看] 项目在什么阶段才能获得LEED得分项的得分?At what point can a project earn points for credits? A: 设计阶段之后 After the design phase B: LEED项目检查表(Checklist)完成并递交之后 After the LEED Project Checklist is completed and submitted C: 工作说明书(statement of work)上传到LEED Online之后 After the statement of work has been uploaded to LEED Online D: 施工阶段之后 After the construction phase 参考答案: D
本题解释: 正确答案:D
系统解析: 暂无解析
D:When a project opts for a split review there are separate reviews for the design phase and the construction phase. For the design phase those credits that can be reasonably assumed will be earned are marked as Anticipated or Denied. For the construction phase the credits will be marked as Awarded or Denied.
Points may be marked as Anticipated in LEED Online after the design phase but points are only Awarded (earned) after the construction phase. This is true of all credits and prerequisites.
A:No points can be earned after the design phase.
B:Uploading the project checklist (LEED Scorecard) does not earn a project points.
C:The project narrative, typical floor plans, and elevations are part of the required documentation for all LEED projects. Uploading this documentation does not earn a project any points. |
|