试卷: LEED v4 GA模拟题A卷中文[查看] 建筑业主选择安装现场风力涡轮机来减少输电网非可再生能源使用,下面哪项是安装现场风力涡轮机的好处?Which of the following is a benefit of a building owner choosing to install a wind turbine on site to reduce the building’s use of grid-source nonrenewable energy?
A: 减少温室气体排放量 Reduced greenhouse gas emissions B: 减轻热岛效应 Heat island reduction C: 较低的负债 Lower liabilities D: 降低前期建筑投资 Decreased up-front building costs 参考答案: A
本题解释: 正确答案:A
系统解析: 暂无解析
A:When renewable energy (wind, geothermal, solar) is chosen over nonrenewable energy (oil, coal, natural gas), greenhouse gas emissions are decreased.
B:Heat islands would not be impacted.
C:Liabilities would not be an issue.
D:The up-front costs will probably be higher unless the owner can find a utility provider to install the system for free and then agree to purchase the renewable energy from the provider. |
|