试卷: LEED v4 GA模拟题C卷[查看] Which of the following is the average payback period for the commissioning of new buildings?
A: 1.5 years B: 2.6 years C: 3.9 years D: 4.8 years 参考答案: A
本题解释: 正确答案:A
系统解析: D:Commissioning can be expensive but, compared to the savings it achieves over time, it’s one of the best investments a building owner can make. There are many studies that show the benefits of commissioning with examples of installation errors that cost building owners thousands of dollars a year unnecessarily.
A study by the Lawrence Berkeley National Laboratory found the following: ’For existing buildings, we found median commissioning costs of $0.27/ft2, whole-building energy savings of 15 %, and payback times of 0.7 years. For new construction, median commissioning costs were $1.00/ft2 (0.6 % of total construction costs), yielding a median payback time of 4.8 years (excluding quantified non-energy impacts).’
|
|