试卷: LEED v4 GA模拟题C卷[查看] If a mechanical engineer on a LEED project team needs guidance on whether a particular software package can be used to measure energy efficiency, how should the engineer proceed? A: Submit a CIR to the project administrator B: Submit a CIR using LEED Online C: Submit a CIR to the LEED Steering Committee D: See if the credit is marked ’Anticipated’ during the design phase review 参考答案: B
本题解释: 正确答案:B
系统解析: B:Because it is unclear whether the strategy applies to the given credit, a CIR must be submitted using LEED Online. The design phase review would not mark a credit as ’Denied’ in this case for choosing one software package over another.
Anyone on the project team (after being added to LEED Online for that project) can submit the CIR, then someone has to cut a check to GBCI for the review.
|
|