What does NOT need to be included in an ongoing commissioning plan to meet the <

[复制链接]

203

主题

0

好友

512

积分

超级版主

Rank: 8Rank: 8

跳转到指定楼层
楼主
发表于 2013-10-9 15:25:12 |只看该作者 |倒序浏览
试卷: LEED AP EB模拟题 D卷[查看]
What does NOT need to be included in an ongoing commissioning plan to meet the
requirements of EA Credit 2.3 Existing Building Commissioning: Ongoing Commissioning?
A: Any changes in occupancy schedules
B: Performance testing frequency
C: Estimated budget for each task that occurs in the commissioning cycle
D: Procedures for responding to deviations from any preferred performance parameters

参考答案: A

本题解释:
Notes:
See EA Credit 2.3, Approach and Implementation
Changes to occupancy schedule, run-times, setpoints, etc., should be updated in the
building operating plan, not in the ongoing commissioning plan. The commissioning plan
should be adjusted based on these changes, but this is not where the changes are
documented.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-7-9 04:34 , Processed in 0.074628 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部