试卷: LEED AP EB模拟题 D卷[查看] What does NOT need to be included in an ongoing commissioning plan to meet the
requirements of EA Credit 2.3 Existing Building Commissioning: Ongoing Commissioning? A: Any changes in occupancy schedules B: Performance testing frequency C: Estimated budget for each task that occurs in the commissioning cycle D: Procedures for responding to deviations from any preferred performance parameters 参考答案: A
本题解释: Notes:
See EA Credit 2.3, Approach and Implementation
Changes to occupancy schedule, run-times, setpoints, etc., should be updated in the
building operating plan, not in the ongoing commissioning plan. The commissioning plan
should be adjusted based on these changes, but this is not where the changes are
documented. |
|