试卷: LEED AP EB模拟题 C卷[查看] In a project team meeting, a building owner expresses concerns over the higher first-cos t
premiums of the sustainable products bei ng considered for the project. What should the
project team do? A: Seek alternative products that have lower costs B: Perform life-cycle costing to show the payback of the products over time C: Incorporate language into tenant lease agreements that require sustainable purchasing D: Select more products from local manufacturers 参考答案: B
本题解释: Notes:
See MR Prerequisite 1, Approach
Life-cycle costing will most likely show t he owner the payback over time of purchasing
sustainable products. Existing products can be replaced as long as the goals of MR P1 are
still met.
Lower cost/local products do not necess arily mean more sustainable products. |
|