A project will have two existing mixed-use buildings that will be renovated. The

[复制链接]

203

主题

0

好友

512

积分

超级版主

Rank: 8Rank: 8

跳转到指定楼层
楼主
发表于 2013-7-24 14:56:08 |只看该作者 |倒序浏览
试卷: LEED AP ND模拟题A[查看]
A project will have two existing mixed-use buildings that will be renovated. The project team is considering a district heating and cooling system. What is true about the project’s ability to earn GIB Credit District Heating and Cooling?

A: The project could earn the credit if at least 80% of the annual heating and/or cooling consumption is provide by the district
B: The project cannot earn the credit because the DHC must service at least 3 buildings
C: The project cannot earn the credit because the DHC must service at least 2 new buildings
D: The project could earn the credit if the project earns at least 2 points under GIB Credit On-Site Renewable Energy Sources

参考答案: A

本题解释:
At least 2 buildings must be services. Single-family residential and existing buildings of any type can be excluded, but it is fine to have them make up the 2 required buildings.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-7-7 13:28 , Processed in 0.075175 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部