What should be included in a construction waste management plan?

[复制链接]

1759

主题

1

好友

5692

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-11-5 15:41:10 |只看该作者 |倒序浏览
试卷: LEED GA模拟题C[查看]
What should be included in a construction waste management plan?
A: If any construction waste materials to be recycled will be commingled or separated
B: New technologies and materials that will help reduce waste
C: The distance products were purchased from the construction site
D: Which existing building materials - if any - will be reused

参考答案: A

本题解释:
Notes:

Reference: LEED 2009 for New Construction and Major Renovations Rating System
The construction waste management plan will describe where construction and demolition debris is going to go. Part of this decision is to use commingled or separate recycling.

B decision would be part of the design plan, not part of how to divert and dispose of waste.

C information is needed for Regional Materials credit.

D decision is part of the design phase where questions might be asked such as \'are we going to reuse the roof of this existing building\'. If the answer is no, then the waste management plan would include information on where the roof is going.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-7-7 11:32 , Processed in 0.072260 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部