试卷: LEED AP BD+C模拟题B[查看] A civil engineer is working with the project team to finalize a construction activity stormwater pollution prevention plan. What must be included in this plan? A: All measures to prevent stormwater contamination, control sedimentation,, and erosion during construction, and comply with th B: Stormwater harvesting measurements C: Quantity of total suspended solids removed D: Pre and post stormwater discharge rates 参考答案: A
本题解释: Notes:
Reference: Sustainable Sites Prerequisite, Construction Activity Pollution Prevention, Definitions
A stormwater pollution prevention plan is part of construction activity pollution prevention (not SS 6 Stormwater Design). The plan must include all measures to prevent stormwater contamination, control sedimentation and erosion during construction, and comply with the requirements of the Clean Water Act
|
|