试卷: LEED GA模拟题E[查看] What tool would a project team use to set the project’s green design criteria? A: Project schedule B: LEED Score Card C: Vision statement D: Construction bids 参考答案: B
本题解释: Notes:
Reference: Sample credit checklist for LEED v3
A:The project schedule should occur later on after the design criteria has been set.
B:The LEED Score Card is a tool that helps the project team decide what specific design criteria will be met.
Usually in the pre-design phase everyone involved in a project will get together either in person or on a conference call and discuss the project\'s green building goals. These goals may have already been set by the project\'s owner based on the project vision, or the team may come up with them at this time. Once the goals are set, the project team will use the LEED score card to check which LEED credits the project is likely to achieve, and/or which credits the project team wants to achieve. This meeting is called the charrette. The LEED score card is a tool to help guide the process and the meeting.
What was just described is a typical approach, but it may not always be followed this way. There are variations but the end result is the same - a completed LEED score card that guides the project from beginning to end. At each step during the project - design, construction, etc, the project team consults the LEED score card to make sure the project is on track to achieve the credits the project team set out to achieve.
C:The project\'s green building goals should be developed from the vision statement. (Sustainable Building Technical Manual: Part II)
However the vision statement is not a tool and not what the question is trying to teach.
D:Construction bids should occur later on after the design criteria has been set. |
|