试卷: LEED AP BD+C模拟题C[查看] The renovation of an existing 50,000 square feet core and shell project will include an addition. The design team would like to earn one point for Materials and Resources credit, Building Reuse: Maintain Existing Walls, Floors & Roof. What is the maximum size the addition can be and still qualify for this credit? A: Adding an addition will disqualify the project for this credit B: 25,000 SF C: 50,000 SF D: 75,000 SF E: 300,000 SF 参考答案: E
本题解释: Notes:
See the‘Requirement’ section of NC MRc1.1, Building Reuse: Maintain Existing Walls, Floors & Roof
The addition must be less than or equal to 6-times the size of the existing building for CS projects to qualify for NC MRc1.1, Building Reuse: Maintain Existing Walls, Floors & Roof |
|