试卷: LEED AP BD+C模拟题D[查看] A new construction project is purchasing salvaged bricks from a local company that
sourced the bricks from local buildings that are scheduled for demolition. The cost of the
bricks was $175 per ton with a shipping charge of $40/ton. The company received a 10%
off discount (excluding shipping) by paying within 15 days. The project will use the bricks
to make the floor of the lobby area and will purchase 10 tons of bricks. What dollar value
should be used for the Materials and Resources Credit, Materials Reuse calculation? A: $1,750 B: $1,575 C: $1,975 D: $2,150 参考答案: C
本题解释: Notes:
Cost and shipping can be included in the calculation of cost for a salvaged item found
off-site, but any discount has to be reflected in the price as well.
($175/ton * 10 tons) + ($40 ton/shipping X 10 tons) - ($175/ton * 10 tons * 10% discount) =
$1,975 |
|