The new addition to a school will not be completed before the new school year be

[复制链接]

203

主题

0

好友

512

积分

超级版主

Rank: 8Rank: 8

跳转到指定楼层
楼主
发表于 2012-8-28 19:44:51 |只看该作者 |倒序浏览
试卷: LEED AP BD+C模拟题D[查看]
The new addition to a school will not be completed before the new school year begins.
Renovations will continue while school is in session, including the installation of
VOC-emitting materials during some mild sunny weather. What should the contractor do
to prevent the contamination of the occupied school?
A: Close the returns on the HVAC grills
B: Use vacuum cleaners with high-efficiency particulate filters
C: Install temporary ventilation units
D: Ventilate using 100% outside air

参考答案: D

本题解释:
Notes:
Reference: Indoor Environmental Quality Credit, Construction Indoor Air Quality
Management Plan-During Construction, Implementation, Pathway Interruption
When VOC-emitting materials are installed the contractor should ventilate using 100%
outside air to keep from contaminating the rest of the school. The space should also be
sealed off and depressurized.
Temporary ventilation units and closing return grills are used for HVAC protection.
Vacuum cleaners are used to clean up dust, not to prevent VOC-emissions.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-5-7 23:06 , Processed in 0.076218 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部