试卷: LEED AP BD+C模拟题C[查看] The project team is discussing commissioning activities in a pre-design meeting to help determine a target certification. What additional tasks will the commissioning authority need to perform for enhanced commissioning? A: Conduct a design review prior to producing mid-construction documents B: Verify installation and performance of systems C: Complete a summary commissioning report D: Develop a Basis of Design 参考答案: A
本题解释: Notes:
Reference: Energy and Atmosphere Credit, Enhanced Commissioning, Requirements
See the requirements for a complete list of the six additional activities required for this credit. |
|