试卷: LEED AP BD+C模拟题B[查看] A new high-rise residential project is going up in a master site development. The site will be connected to an off-site master stormwater management system. What is true about the project’ s ability to achieve Sustainable Sites Credit Stormwater Design - Quantity Control? A: The project can only earn the credit if the area of the development boundary has an existing imperviousness of 50% or less B: The project can only earn the credit if BMPs are followed by all buildings connected to the stormwater system C: The project can only earn the credit if the stormwater system meets LEED requirements for all drainage areas that it serves D: The project can only earn the credit if the original master planned site was previously developed 参考答案: C
本题解释: Notes:
Reference: SS Stormwater Design, Quantity Control, Implementation
See page 94 of the reference guide: Master Site Development Considerations.
|
|