| 试卷: LEED AP ID+C 模拟试卷B[查看] The total CSI MasterFormat Division 12 Material Value on a project is $1,000,000. Reused workstations from the owner’s former office site will be used on the project. The replacement value of the workstations is $200,000. The market value of the workstations is $100,000. How much additional salvaged material will the project team need to add to earn Materials and Resources Credit, Materials Reuse?
 A: $200,000
 B: $300,000
 C: $400,000
 D: $100,000
 
 参考答案: D
 
 本题解释:
 Reference: Materials and Resources Credit, Materials Reuse-Furniture and Furnishings
 For resource reuse of furniture and furnishings, the credit calculation must be 30% or greater. These calculations are based on the replacement value of furniture, not its market value.
 
 $1,000,000 X 0.30 = $300,000 in salvaged material is needed.
 
 Since the project already has $200,000 of salvaged furniture, an additional $100,000 of salvaged furniture will be needed.
 
 | 
 |