试卷: LEED AP BD+C模拟题B[查看] A school project is near rural farmland. The project site was previously a retail location.
The site area is large and equals 500,000SF while the building footprint will only be 50,000 SF. A majority of the area will be restored with native and adaptive plants. Water runoff
methods will include cisterns, vegetated swales, and open grid paving. Open grid paving
takes up 30,000 SF. What is the minimum amount of land that could be restored to earn
exemplary performance under Sustainable Site Credit 5.1 Site Development - Protect and
Restore Habitat? A: 135,000 SF B: 337,500 SF C: 450,000 SF D: 420,000 SF 参考答案: B
本题解释: Notes:
To earn exemplary performance point for SS Credit 5.1 the project must restore 75% of the site
excluding the building footprint or 30% of the site including the building footprint, whichever is
greater.
(500,000SF - 50,000) *.75 = 337,500
500,000 * 0.3 = 150,000 |
|