试卷: LEED AP BD+C模拟题E[查看] You are the LEED Administrator on a project and the contractor has stated that the amount of waste to be diverted from landfills will not be 50% of the total amount of waste, if measured by weight. Is there another option to earn a point for Materials and Resources credit, Construction Waste Management? A: Yes, a point can be earned for diverting 25% of waste from landfills B: Yes, the waste to be recycled can be calculated by volume C: Yes, an exemplary performance point can be earned if enough concrete is diverted from landfills D: No, there is no other option to earn a point 参考答案: B
本题解释: Notes:
MRc 2, Construction Waste Management, calculations can be done either by weight or by volume. If heavier materials are being diverted it would be beneficial calculate by weight. |
|