A design team is attempting to earn a point for Sustainable Sites credit, Site D

[复制链接]

1759

主题

1

好友

5692

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-9-29 17:12:27 |只看该作者 |倒序浏览
试卷: LEED AP BD+C模拟题E[查看]
A design team is attempting to earn a point for Sustainable Sites credit, Site Development: Protect or Restore Habitat. The project has met the requirements of Sustainable Sites credit, Development Density & Community Connectivity. What are some potential strategies for achieving Sustainable Sites credit, Site Development: Protect or Restore Habitat? (choose 2)
A: Replace a portion of hardscape with native plants
B: Increase the amount impervious surfaces
C: Add a vegetated roof to the building
D: Add some additional hardscape around the building
E: Add mulch around all landscaping

参考答案: AC

本题解释:
Notes:
See the “Requirements” and “Potential Technologies & Strategies” sections of NC SSc5.1, Site Development: Protect or Restore Habitat
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-7-6 10:02 , Processed in 0.077534 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部