The mechanical contractor, working on a new office building, has installed monitoring systems that provide feedback on ventilation system performance in an effort to comply with Indoor Environmental Quality credit, Outdoor Air Delivery Monitoring. At what point should these monitoring systems generate an alarm?
A: When conditions vary by 5% from a set point
B: When conditions vary by 10% from the value expected at design conditions
C: As defined in ASHRAE 62.1-2004
D: When CO2 levels reach dangerous levels
E: When oxygen levels drop below 20%

参考答案: B

本题解释:
Notes:
See the ‘Requirements’ section of IEQc1, Outdoor Air Delivery Monitoring.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-7-6 08:04 , Processed in 0.072184 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部