试卷: LEED AP BD+C模拟题B[查看] What should be included in a construction waste management plan for the demolition
of an existing building? A: Where to dispose of any PCBs B: The design of the size of the building C: The removal of any CFC-based refrigerants D: Installation of a composting system for occupants 参考答案: A
本题解释: Hazardous material removal is part of the plan. Hazardous materials do not
count toward the percent of debris diverted from landfills but they are still
included in the waste management plan.
The size of the building impacts the quantity of construction waste, but this
decision is not part of the construction waste management plan.
CFC removal would be done by a specialist. This would not be part of the
waste management plan.
Composting would occur post-construction when the building has occupants.
Reference: LEED 2009 for New Construction and Major Renovations Rating System |
|