试卷: LEED AP BD+C模拟题E[查看] A baseline analysis was performed and a building was found to potentially use 1,000,000 gallons of potable water for sewage conveyance per year. The design team for this building would like to earn three points for Water Efficiency credit, Innovative Wastewater Technologies. Treating waste water on-site is not an option. What amount of potable water could be used for sewage conveyance and still accomplish this goal? A: 0 gallons B: 200,000 gallons C: 400,000 gallons D: 500,000 gallons E: 750,000 gallons 参考答案: A
本题解释: Notes:
See the “Exemplary Performance” section of WEc 2
The only way to earn 3 points for NC WEc2, Innovative Wastewater Technologies is to achieve exemplary performance and demonstrating 100% reduction in potable water use for sewage conveyance. |
|