A project for a previously developed site has a slope over 40% that will require

[复制链接]

203

主题

0

好友

512

积分

超级版主

Rank: 8Rank: 8

跳转到指定楼层
楼主
发表于 2013-8-27 10:04:58 |只看该作者 |倒序浏览
试卷: LEED AP ND模拟题A[查看]
A project for a previously developed site has a slope over 40% that will require 100% restoration to earn SLL Credit Steep Slope Protection. What else will the project team need to do to earn the credit?

A: Limit development to within 100 feet around the slope
B: Develop covenants, conditions, and restrictions (CC&R) to protect the slope in perpetuity
C: Limit development to within 50 feet around the slope
D: Implement a stormwater management plan to protect the slope from erosion

参考答案: B

本题解释:
CC&Rs are required for this credit for both Option 2 and Option 3.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-7-7 20:20 , Processed in 0.075993 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部