试卷: LEED AP ND模拟题A[查看] A project is located on a site with no wetlands and no water bodies. What must occur for the project to earn SLL Prerequisite Wetland and Water Body Conservation? A: The site must be located 100 feet from any wetlands and 100 feet from any water bodies B: The site must be located 50 feet from any wetlands and 50 feet from any water bodies C: Nothing, the requirements are met because no wetlands and no water bodies are on the site D: The site must be located 50 feet from any wetlands and 100 feet from any water bodies 参考答案: D
本题解释: If the site doesn\'t have a wetland or water body, the site must still have a buffer around it from wetlands and water bodies outside of the given limits |
|