试卷: LEED AP EB模拟题 A卷[查看] A building is undergoing its first commissioning cycle. What is NOT true for the projec t
to earn EA Credit 2.3 Existing Building Commissioning: Ongoing Commissioning? A: At least half of the scope of work must be completed B: The completed tasks must be documented using actual costs C: The work must be completed within two years of the application date D: The written plan can be summarized by building system group 参考答案: B
本题解释: Notes:
See EA Credit 2.3, Requirements
The written plan can be summarized by equipment or building system group.
For the first commissioning cycle, at least 50% of the work scope must be completed.
The work must also be completed with in two years of the application date.
The completed commissioning tasks can be based on estimated costs or actual costs. |
|