试卷: LEED v4 GA模拟题A卷[查看]
A project team is beginning the integrative process late into the design-phase of a new office building. At this point, which of the following could still be changed and would be a low-cost solution for improving daylighting?(Choose 2)
A: The number of glazing panes
B: The orientation of the building
C: The colors of the surfaces
D: The types of furnishings
E: The window configuration

参考答案: CD

本题解释:
Notes:

While all of the choices impact lighting, changing the types of furnishings and the colors of the interior are inexpensive strategies to improve daylighting and reduce glare, both of which would increase the quality of the indoor lighting.

分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-9-13 01:00 , Processed in 0.074079 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部