试卷: LEED v4 GA模拟题C卷[查看] What document does the project team create for the administrative and procedural requirements for salvaging, recycling, and disposing of non-hazardous demolition and construction waste? A: Owners Project Requirements (OPR) B: Building commissioning plan C: Construction waste management plan D: Building recycling plan 参考答案: C
本题解释: 正确答案:C
系统解析: C:A construction waste management plan contains the administrative and procedural requirements for salvaging, recycling and disposing of non-hazardous demolition and construction waste.
B:The commissioning plan is a document that outlines the organization, schedule, allocation of resources, and documentation requirements of the commissioning process.
D:The building recycling plan addresses how materials should be collected and stored for recycling, once the building is occupied.
|
|