A project team is working in China that does not have WaterSense equivalents for

[复制链接]

1759

主题

1

好友

5712

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2015-4-13 09:15:01 |只看该作者 |倒序浏览
试卷: LEED v4 BD+C英文模拟题(A)[查看]
A project team is working in China that does not have WaterSense equivalents for fixture performance. For the prescriptive compliance path of WE Prerequisite Indoor Water Use Reduction, which action should the project team take to achieve the prerequisite?
A: Use alternative water sources to show a reduction in potable water use
B: Exclude the fixtures as necessary to show compliance
C: Select a fixture performance of at least 20% below the baseline of EPAct 1992
D: Use calculations to show compliance

参考答案: C

本题解释:
正确答案:C
解析:C:Countries that do not have WaterSense equivalents must comply with the fixture performance requirement that water use at least 20% below baseline and the EPAct’s 1992 requirement.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-9-14 04:31 , Processed in 0.076528 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部