试卷: LEED v4 BD+C英文模拟题(A)[查看] A neighborhood project is planning on certifying to LEED ND Plan.There are several LEED projects in the neighborhood that have substantially completed designs.Which action sequence will help streamline the documentation process? A: Earn certification for all buildings first before submitting the LEED ND project for certification B: Complete the building design review phase first,then the LEED ND Plan certification C: Earn certification for all buildings first before registering the LEED ND project D: Submit the LEED ND project for certification,then wait until approval before submitting the buildings 参考答案: B
本题解释: 正确答案:B
解析:C:If this were done,the LEED BD+C projects could not earn LT Credit LEED ND Location.
D:Because of the overlap in the building and water prerequisites,it is better to submit the buildings first. |
|