试卷: LEED v4 ID+C模拟题B卷英文[查看] Which statement is true regarding construction checklists as part of the commissioning process? A: Test sampling is prohibited even if the project contains a large number of identical systems. B: Testing and balancing are not included in the checklist. C: The contractor is responsible for filling out the checklist and returning it to the CxA. D: The checklist confirms the contractor has completed functional testing. 参考答案: C
本题解释: 选择C,本题解释A.For the prerequisite, the commissioning authority may use sampling strategies for functional testing. B.The checklist ensures that the systems have been installed, started up, programmed, tested, and balanced and are ready for functional testing. C.This is true. D.The checklist ensures that the systems have been installed, started up, programmed, tested, and balanced and are ready for functional testing. |
|