试卷: LEED v4 ID+C模拟题B卷英文[查看] The owner of a tenant space has had a lot of turnover in the project team, resulting in delays in LEED documentation. How long can the project team wait to submit the construction phase review (preliminary standard review or preliminary construction review)? A: No later than two years after the project is substantially completed B: No later than 18 months after any new version of LEED is released C: No later than two years after signing the lease agreement D: No later than 18 months after project registration 参考答案: A
本题解释: 选择A,本题解释Deadline for submitting for review
For LEED BD+C and LEED ID+C rating systems, you will need to submit for your construction phase review (preliminary standard review or preliminary construction review) no later than two years after your project is substantially completed (the date on which your building receives a certificate of occupancy or similar official indication that it is fit and ready for use). |
|