After an office space was completed in June, a project team took daylight measurements in all regularly occupied spaces. Which action must occur for the project to earn EQ Credit Daylight?
A: A narrative must be written listing the compliant spaces with their calculated illuminance values.
B: The team must submit a list of compliant spaces with their annual summary values for sDA and ASE.
C: A daylight modeler must be hired to confirm the results of the measurements.
D: A second set of measurements must be taken in October to determine compliant floor areas.

参考答案: D

本题解释:
选择D,本题解释 A.There are no calculations for Option 3. B.This is only for Option 1. C.Daylight modelers aren\'t required for Option 3.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-9-12 23:25 , Processed in 0.087668 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部