试卷: LEED v4 ID+C模拟题C卷英文[查看] Which non-mandatory steps could a project team take prior to conducting air-quality testing that would improve the test results for EQ Credit IAQ Assessment?(Choose 2) A: Complete punch-list items that would generate VOCs or other contaminants B: Vacuum using a vacuum cleaner with filtration media C: Test and balance the HVAC system D: Clean with low-emitting cleaning products E: Install finishes and furniture 参考答案: BD
本题解释: Notes:
Here are the required steps before a flush-out or air testing:
Install all finishes and furniture
Complete punch-list items that would generate VOCs or other contaminants
Test and balance the HVAC systemB:This is non-mandatory before a flush-out or air testing.D:This is non-mandatory before a flush-out or air testing. |
|