试卷: LEED v4 ID+C模拟题D卷英文[查看] A project team is pursuing EA Credit Enhanced Commissioning. When does the building operations need to be reviewed? A: Twelve (12) months after LEED certification has been awarded B: Ten (10) months after substantial completion C: Ten (10) months after the functional tests are completed D: Twelve (12) months after occupancy 参考答案: B
本题解释: 选择B,本题解释The CxA must be involved in reviewing the operation of the building with operations and maintenance (O&M) staff and occupants within 10 months after substantial completion. A plan for resolving outstanding commissioning-related issues must be included. |
|