试卷: LEED v4 OM模拟题C卷英文[查看] A project team is discussing synergies to achieve both SS Credit Rainwater Management and SS Credit Heat Island Reduction. The project design will include covered parking. Which strategy would help earn both credits?
某项目团队正在讨论SS 得分项雨水管理和热岛效应降低的协同性。该项目设计中包含了有盖停车场。哪项策略有助于取得这两分? A: Include a photovoltaic system that will recharge green vehicles 安装光伏系统为绿色汽车充电 B: Include a vegetated roof 种植屋顶 C: Include parking by shaded by trees 包含被树荫遮盖的停车位 D: Include decking with a three-year aged SRI of at least 32 包含三年SRI至少为32的遮盖板 参考答案: B
本题解释: 选择B,本题解释Any roof used to shade or cover parking must (1) have a three-year aged SRI of at least 32 (if three-year aged value information is not available, use materials with an initial SRI of at least 39 at installation), (2) be a vegetated roof, or (3) be covered by energy generation systems, such as solar thermal collectors, photovoltaics, and wind turbines.
When considering rainwater management look at LID/GI strategies.
Only the vegetated roof accomplishes both goals. |
|