A school project is expected to have 745 students in grades K-8 and is located 1

[复制链接]

1759

主题

1

好友

5684

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-12 16:22:18 |只看该作者 |倒序浏览
试卷: LEED AP BD+C模拟题A[查看]
A school project is expected to have 745 students in grades K-8 and is located 1/2 mile from a high school which has 972 students in grades 9-12. There are three planned walking routes that go to the school property line. The school has three school buses that bring students to the school’s front door. What is true about the project’s ability to earn Sustainable Sites Credit, AlternativeTransportation-Public Transportation Access?
A: The three school buses would earn the credit
B: If 610 students live within 3/4 mile walking distance to the school the project would earn the credit
C: The walking routes would earn the credit
D: If 590 students live within 3/4 mile and 778 within 1.5 miles walking distance of school the project will earn this point

参考答案: B

本题解释:
Notes:
To earn a point for earn Sustainable Sites Credit, Alternative Transportation-Public Transportation
Access the school must have an attendance boundary where at least 80% of students live within no
more than 3/4 mile walking distance for grades 8 and below. The project mentioned in the
question is for grades K-8. The project expects 745 students, so 80% within 3/4 mile would equal
596 students.
The information about the high school is just a distraction. It is common to see these types of
distractions in standardized tests, so it is important to pay close attention to the information that
really matters for each question.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-5-3 05:51 , Processed in 0.075862 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部