试卷: LEED v4 OM模拟题A卷英文[查看] What credit requires developing a five-year plan for equipment replacement and major modifications or upgrades?
哪个得分项要求为设施更换或者重大改造更新制定一个五年计划? A: EA Credit Existing Building Commissioning - Analysis EA得分项 既有建筑调试-分析 B: EA Credit Existing Building Commissioning - Implementation EA得分项 既有建筑调试- 执行 C: EA Prerequisite Energy Efficiency Best Management Practices EA先决条件 最佳节能管理实践 D: EA Credit Ongoing Commissioning EA得分项 持续调试 参考答案: B
本题解释: 选择B,本题解释 Return to the list of building upgrades identified in the analysis phase that have capital costs and create a five year plan for equipment replacement or major modifications or upgrades. |
|