A project team is using a tenent-level energy simulation for EA Credit Optimize Energy Performance. All of the following quality assurance checks would be flagged by the reviewer except:
A: The baseline and/or proposed interior lighting equivalent full load hours differs by more than 10%
B: The exterior lighting power in the baseline and/or proposed model shows zero consumption
C: The vertical glazing areas in the proposed and baseline differ by more than 5%
D: The baseline vertical glazing area is less than 40%
E: The baseline and/or proposed exterior lighting equivalent full load hours is greater than 5,1000 hours /year

参考答案: D

本题解释:
Notes:See the Minimum Energy Performance Calculator Summary Tab:
http://www.usgbc.org/resources/minimum-energy-performance-calculator
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-6-24 09:00 , Processed in 0.082337 second(s), 34 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部