试卷: LEED v4 ID+C模拟题A卷英文[查看]   A project will include a unique manufacturing process resulting in non-regulated load savings. Which statement is true regarding how these savings would be addressed in a tenent-level energy simulation?   A: The exceptional calculation method would be used B: The savings would be excluded C: The savings do not have to be modeled and no documentation would be required D: The non-regulated load is subtracted from both the baseline and design case model     参考答案: A 
  本题解释: Notes: A non-regulated load is \'any building load, end-use or control which does not have an ASHRAE 90.1-2010 baseline modeling requirement that allows the load and use or control to be modeled differently in the proposed and baseline buildings.\' - USGBC |   
 
  
 |